Town Paving Schedule

Expected impacts
Town logo

October 19, 2021 (Chesapeake Beach, MD)- The Town of Chesapeake Beach has begun making improvements to roadways in Town. Residents impacted have received notices at their dwellings per the outline provided below.  

  1. C Street- Paving is completed.
  2. Harbor Road- Paving is in process today, October 19th, there are no issues with access.
  3. B Street, 11th and 12th Street – Milling will begin Wednesday, October 20th, paving will begin Thursday, October 21st. Residents should plan for limited access on Wednesday the 20th and no access between 8am-5pm on the Thursday the 21st. In the event of emergency, or needed access, please coordinate with the Town by calling (410)257-2230. 
  4.  27th, 28th, 29th, E & F Streets Paving of the alley between 27th & 28th from G to F is expected to start on Friday October 22nd and be completed by Monday October 25th, depending on weather. Access will remain open.
  5. Chesapeake Village: sealing will take place in the coming week.

Thank you for your patience as we make these needed improvements. 

###